Land sinking fear forces slowdown

PANJIM: The mega Rs 136 crore sewerage lines project at Taleigao-Caranzalem and adjoining areas linking them to the new 12.5 MLD treatment plant has hit a road block due to the fear of land sinking and excavation difficulties.

TEAM HERALD
PANJIM:  The  mega  Rs 136  crore sewerage  lines project  at Taleigao-Caranzalem  and  adjoining areas linking them to the new 12.5 MLD treatment  plant  has  hit  a road  block due to the fear of land sinking and excavation difficulties.
The PWD has,  therefore, been forced to go slow on its on-going  works  at  Taleigao. It is now preparing  a plan for revision of the  project designs  due  to  increasing  excavation difficulties.
A  top  source  in the  Public  Works  Department (water and sanitation)  told Herald  that  on-going  works  for  laying sewerage  lines are  facing  severe  problems  as  the  high  water  table  in the  Taleigao  belt   is hampering work  of  laying sewerage  lines measuring about  four  kilometres  in length.
“The  ground water  table  is  so high  that  the trenches dug are getting  filled  with  water instantly. This  compels  us  to  flush out  the  water  more  frequently  than  required,”  said this  official.
The  PWD  has, however,  realised  that  round-the-clock  flushing out  of  water, though required, may have  adverse consequences  for  residential  colonies  in close  proximity.
“If we  keep on  draining  out  the  water, it  could  cause  en masse  sinking  of the  soil and a  threat to nearby residential  colonies and houses,”  he said adding  that  the  PWD  is not  willing to  take  any such  chances that could  endanger property and  life.
While  technical options  of  compacting or  consolidation of the  soil   would  not  work to the  advantage  of the  department’s  on-going  work~ which  officials say is already  running  behind schedule~ plans  have been submitted  for  re-designing much of the   work left to be  completed  in  Taleigao itself.
When contacted Chief  Engineer (CE-I) D S Borkar said, “We  have  submitted  a plan to the  government   for  revision  of  the project designs.” This  is only  for the pending work in the  areas  of  Taleigao.
According to the  revised  plans,  the  PWD  proposes  to  lessen the  depths for  excavation by  at  least  two to  three meters so as  to  avoid  contact  with the  ground water table.
“While this  may  reduce  the  gravity required  for facilitating flow  of  sewage  through the pipelines we are also proposing to  increase  the  number  of  pumping  stations  for Taleigao  area,”  Borkar  said.
We  are also  given to understand  that  the  cost   of  the project  may  go up by  10  per cent if  the plans are  revised  for Taleigao.
So far work  on only one  kilometre  stretch  has  been completed out of the close  to five  kilometres stretch of Taleigao proposed  to be  covered  under  the  new  scheme.
Work  had started in  January 2013 and the  PWD  says it is  difficult  to  give  a deadline  as to when  it  would  complete the  works  in Taleigao.

Share This Article